after a protracted section of preparatory paintings, construction of the 47-km dhaka accelerated parkway started out officially on april 1, 2018.

within a short period of time the limited-access highway scheme to date made an common development of ten percent. meanwhile, the 7.five-lengthy first phase, which covers the area from shahjalal global airport to banani, has improved by a qyarter.

consistent with the undertaking director quazi muhammad ferdous, the freeway scheme has to this point made an average ten percentage development, even as the 7.5 km-long first phase stretching from hazrat shahjalal worldwide airport to banani has advanced with the aid of a quarter.

“through october 2020, we expect the throughway can be prepared as much as moghbazar, and be open for public use,” he said even as talking about the general progress of the mission.

“the limited-access highway is designed to hold motor cars traveling to the city’s southern end, easing traffic pressure at the center city location,” he went on to feature.

to date, the authorities has made a few progress which includes guidance of a construction backyard via airport road, acquisition of 26 acres non-public land, resettlement, construction of a few piers, transferring of software carrier line and demolition of systems on the manner of the throughway, ferdous remarked.

the work is now happening full swing within the complete 71-acre land which is needed for the primary phase while acquisition of closing 149 acres has also been carried out.

presently, the resettlement price to the affected people is going on, ferdous delivered.

earlier, a deal became signed with the bridge authority and ital-thai development public corporation in january 2011 to build the freeway stretching from shahjalal global airport to kutubkhali at the dhaka-chittagong dual carriageway.

the value of the undertaking, underneath public-private-partnership, was estimated tk 8,703 crore.

a few modifications were made in a while and a revised deal become signed again in december 2013 among the 2 celebration with the revised fee at tk 8,950 crore.

the authorities is to spend tk four,885 crore on land acquisition, resettlement and relocation of software provider lines which takes the tally of total price of the task at tk thirteen,825 crore.

ferdous said around sixty five percent of the whole cash allotted for floor coaching expenses is already spent by way of the authorities to speed up the challenge.

after finishing all sorts of preparatory paintings, the authority involved started the physical paintings informally in august 2016.

the 57km lengthy proposed course of the limited-access highway is supposed to cowl hazrat shahjalal global airport-kuril-banani-mohakhali-tejgaon-moghbazar-kamlapur-saidabad-jatrabari and dhaka-chittagong highway in kutubkhali.

the first section is almost 7.5km lengthy, the second is 6km and the third phase is 6.5km lengthy whilst the mega-venture requires in overall 220 acres of land.